Project Specification

Concrete Pour Size 5,000 ㎡

Tolerance achieved SR3

Concrete Laid per day 850 ㎥


Our team installed Concrete Service Yards for the Cardinal Maritime warehouse in just 3 months (1 month ahead of schedule).


We completed 5000m2 Brush Finish for the External Yard in addition to the internal warehouse slabs (2,200m2 ) using Laser screed lay and 600m2 of Raised Decking Floor with a Powerfloat finish.


“CBS installed Service Yard concrete slabs and completed one month ahead of schedule"