Project Summary
CBS completed a 3m high retaining wall, 100m in length. The works included a base slab, with 4T of loose reinforcement, then a 3m high wall, including 29T of loose reinforcement, all shuttering with a pan system and pouring of the wall using a concrete pouring skip & excavator. The wall was completed in 9nr pours.