top of page

Larsen Trade Park

Project Specification

Concrete Pour Size 1000 ㎡

Tolerance achieved SR3

Concrete Laid per day 200 ㎡


We provided external yard concreting for our clients JP Wild Group at Larsen Trade Park.


Our team hand laid a total of 1,000m2 concrete with a brush finish.


The entire project consisted of reinforcement, isolation and joints and all was completed within 1 week.


“We had concrete installed for our external yard. CBS were tidy, safe & completed our project in just 1 week"

Project Summary




































Comments


bottom of page