Raised Concrete Floors with Powerfloat Finish
Project Specification
Concrete Pour Size 2,280 ㎡
Tolerance achieved SR3
Concrete Laid per day 53 ㎥
Our team installed raised concrete floors with a Powerfloat finish for our repeat client Mansell Finishes on Northgate Student Housing.
At this project we completed a new student housing comprising 6 storeys concrete slabs on metal decking.
Total job size 2,280 m².
“CBS installed raised concrete slabs for Northgate project at Chester, a 6 storey student housing development with an area of 2,280 ㎡”
Project Summary
Comments